CORREN POSITION: HOME1 > NEWS CENTER > News

The Load Throw-Off Test of Unit-1 of PLTU Sumbar 2x112MW Contracted by CNTIC Has Succeeded on Its First Try

Source: Author: Date:2014-02-12【Font:B M S

The unit-1 of PLTU Sumbar 2x112MW has passed the 50% load throw-off test at 22:18 p.m. on Feb.7, and passed the 100% load throw-off test at 22:34 p.m. on Feb.8, both on their first try. With all the indices shown normal,the unit ran stable.