Overseas Attractions: the Unit-1 of 2×660mw Super Critical Coal Fired Thermal Power Project Contracted by CNTIC Finished the First Phase of the Boiler Blowing

Source: Author: Date:2016-04-08【Font:B M S


On April 5, 2016, the Unit-1 of 2×660mw Super Critical Coal Fired Thermal Power Project contracted by CNTIC finished the first phase of the boiler blowing. Unit-1 started the boiler blowing work on March 23, 2016 and finished on April 5, 2016, altogether blowing 167 times.